WASTE-TO-FUEL. Investment project for the construction of a complex for the provision of the waste reception and recovery services using MBT technology

TECHNICAL INDICATORS OF THE COMPLEX:

FINANCIAL AND ECONOMIC INDICATORS:

  • Project structure based on PPP
  • The investment part is 34.6 million euros
  • Revenue  – 60.45 euros / ton
  • The expenditure part is 28.41 euros / ton
  • Tariffs – progressive model
  • Net discounted profit of the project, NPV – 36.7 million euros
  • Internal rate of return, IRR – 30%
  • Design and construction period – 2 years
  • The project period is 10 years
  • Discounted payback period of the project, DPP – 5 years